Circuit Florida’s first phase of construction is complete. Our membership and condo sales office is open and located within our first club building.

Construction is well underway on two of Circuit Florida’s two-story, townhome-style residential condominium buildings. The completion of the track and the club’s grand opening for members is planned for the weekend of December 16/17.

Phased Construction

  • Onsite construction started May 2022
  • The current construction status is as follows…
    • Circuit Florida’s first club building is finished and open 
    • The canopy-covered paddock/parking area is finished 
    • Onsite membership and condo sales office is open
    • Our first two condo buildings are under construction (12 total units)
    • 1.7 mile circuit (track) continues under construction
    • All site utility work is completed
    • All interior roads are paved
  • Paving of the track is scheduled for the weekend of November 10-12
  • Track curbing and striping to occur between November 27 and December 8
  • Club opens to members on Saturday December 16